Building A Church in Helena, Arkansas
Work is ongoing during most weekdays, but varies. Call Russell Miller
(501.454.4844) if you plan to help or have questions. Sheet rock the sanctuary.
Sheet rock finishers will be hired to complete the job.
The electrician continues to finish his part of the job.
The plumbers are installing gas lines, testing water lines and getting measurements for fixtures.
The heat & air crew will work after Thanksgiving.
At that point the remaining work will be: the ceiling grid, ceiling tile, final insulation, paint, carpet, pews, lights and fixtures.
Goal for completion is early Spring 2008.